History

  • Year 2001 Hydrogen generator was started to be constructed and installed in Hydrogen Station on-site.
  • Year 2002 Undertake the general contract construction of the first hydrogen station.
  • Year 2012 Small hydrogen generator HyGeiaA was developed and on sale.
  • Year 2013 Undertake the general contract construction of commercial Hydrogen Station.
  • Year 2014 Empirical project of Hydrogen station with Sewer gas as the feedstock was carried out.
  • Year 2017 Empirical hydrogen station was arranged in our own company.

Components

Note:The maximum design pressure of hydrogen station is 82MPa.

Total contracted construction projects of Hydrogen Station Plant: 16 sets

 

Businesses of contracted construction

Note:The maximum design pressure of hydrogen station is 82MPa.

Undertake series businesses of hydrogen station including the basic design, the detailed design, equipment installation, engineering construction and start-up for commissioning.